96% of TOGG Gemlik facility has been completed

A post was made on TOGG’s Twitter account regarding the work at the Gemlik facility. It is reported that 96% of the facility, 92% of the hull facility and 89% of the assembly facility have been completed.

The video in the post also included the following information: “Work at our Gemlik facility is progressing in line with our plans. 96% of the paint facility has been completed. Tests of paint tanks and furnaces have begun. 63 thousand 933 meters of electrical wiring has been made. 26 thousand 711 meters of pipeline has been laid. The hull facility is 92% complete. Production line robot layout is completed. 24 thousand 157 meters of electrical wiring was done. 48,684 meters of pipeline was laid. The assembly plant is 89% complete. 29 thousand 216 meters of electrical wiring was done. 53 thousand 335 meters of pipeline has been laid.”

Source: Sabah / Translated by Irem Yildiz